|
STS-91 (91)
- Discovery (24)
- Pad 39-A (66)
- 91st Shuttle Mission
- 24th Flight OV-103
- 1st flight SLWT
- NOTE: Click Here for Countdown Homepage
- Charles J. Precourt (4), Commander
- Dominic L. Pudwill Gorie (1), Pilot
- Wendy B. Lawrence (3), Mission Specialist
- Franklin R. Chang-Diaz (6), Mission Specialist
- Janet L. Kavandi (1), Mission Specialist
- Valery Victorovitch Ryumin (4), Mission Specialist
- Download:
- Andrew S. W. Thomas (Mir-25/STS-89) will return
Milestones:
- OPF -- 08/19/97 (Reference KSC Shuttle Status 08/19/1997)
- VAB -- 10/01/97 (Storage)
- OPF2 -- 10/30/97 (Reference KSC Shuttle Status 10/30/1997)
- VAB -- 04/27/98 (Reference KSC Shuttle Status 4/28/1998)
- PAD -- 05/02/98 (Reference KSC Shuttle Status 5/04/1998)
- FRR -- 05/19/98 (Reference KSC Shuttle Status 5/18/1998)
Payload:
- Mir-Docking/9, AMS, SPACEHAB-SM, GAS(G-722, G-743)
- (Reference KSC Shuttle Status May 1998)
- (Reference KSC Shuttle Status Jun 1998)
Mission Objectives:
Click here for Additional Info on STS-91
- STS-91 will mark the final Shuttle/Mir Docking Mission. This Phase 1
Program is a precursor to the International Space Station maintaining
a continuous American presence in space and developing the procedures
and hardware required for an international partnership in space.
- STS-91 will also carry into space the Alpha Magnetic Spectrometer
Investigation (AMS). The objectives of this investigation are to
search for anti-matter and dark matter in space and to study
astrophysics.
- The mission will also be the first use of the super lightweight
external tank (SLWT) which is the same size (154ft long and 27ft in
diameter) as the external tank used on previous launches but 7,500 lbs
lighter. The tank is made of an aluminum lithium alloy and the tank's
structural design also has been improved making it 30% stronger and 5%
less dense. The walls of the redesigned hydrogen tank are machined in
an orthogonal waffle-like pattern, providing more strength and
stability than the previous design. These improvements will provide
additional payload capacity to the International Space Station.
(Reference NASA Press Release 98-6)
Launch:
- Launch June 2, 1998 6:06:24 p.m. EDT at the opening of the 10
minute launch window.
- On Tuesday, June 2, 1998 launch preparations continued on schedule.
Go for tanking was given at 9:30am after receiving a briefing about
the readiness of the Mir Space station. By noon, at the T-minus 3 hour mark,
LH2 cryogenic propellant loading was complete and in stable
replenish mode. Loading of the Liquid Oxygen tank was about 80%
complete. At 12:30am EDT, tanking operations were complete and
the external tank was in stable replenish mode. The crew departed
the Operations and Checkout Building at 2:19pm EDT, traveled to
Launch Pad 39A and were installed into the orbiter by 3:30pm EDT.
At 4:02pm EDT the Discovery's hatch was closed for flight. At
5:47pm EDT and T-minus 25 minutes and counting the white room close
out was complete and the closeout team left Launch Pad 39A. At
T-minus 14 minutes and holding, the mission management team decided
to move the T-0 time to the opening of the launch window at 6;06pm EDT.
At 5:15pm EDT, the countdown entered a planned 40 minute hold at the
T-minus 9 minute and holding mark. At 17:57 EDT the coundown
came out of the T-minus 9 minute hold with the only concern being
tracked was a slightly low pressure on the Orbiter Access Arm (OAA).
The OAA retracted successfully at 17:59 EDT. Liftoff occured
at 6:06pm EDT. SRB Sep 2.5min into flight, downrange 56 miles.
-
- On Monday, June 1, 1998, launch preparations continued on schedule
and final preflight preparations of Shuttle main engines concluded.
On Tuesday, at about 12:30 a.m. the Rotating Service Structure will be
retracted into the launch position. Loading of the external tank with
its flight load of cryogenic propellants begins at about 9:14
a.m. 6/2/98 and continues for about 3 hours. Managers continue to
monitor the situation with Mir's motion control computer. At this
time, systems aboard Mir have stabilized sufficiently for managers to
proceed with countdown operations. A final check of Mir's systems will
occur prior to tanking activities tomorrow morning.
(Reference KSC Shuttle Status 6/1/1998)
- On Sunday, May 31, 1998, The countdown for launch of mission STS-91
began as scheduled at 9 p.m. 5/30/98 at the T-43 hour mark. All
pre-launch activities at Kennedy Space Center.continue without problem
toward a target lift-off time of 6:10 p.m. on Tuesday, June 2, from
Launch Pad 39A. Today at KSC, engineers are preparing the Shuttle
Discovery for the loading of cryogenic reactants into the onboard
power reactant and storage distribution tanks. Loading is set to begin
at about 5 p.m. Prior to this operation, a standard orbiter and solid
rocket booster pyrotechnic initiator controller test will be
performed. Cryogenic loading operations are expected to conclude by
midnight tonight. (Reference KSC Shuttle Status 5/31/1998)
- On Saturday, May 30, 1998 The countdown for launch of mission STS-91
remains on schedule to begin tonight at 9 p.m. at the T-43 hour mark.
All prelaunch activities continue on schedule. The contingency space
suits have been installed into the orbiter's airlock and check-out of
those suits completed. Flight crew equipment stowage in the orbiter's
mid-deck continued and aft main engine compartment close-outs were
completed and final main propulsion system checks under way. The crew
for mission STS-91 arrived at KSC's Shuttle Landing Facility at about
12:50 p.m. EDT. They will spend the days prior to launch at KSC
reviewing their flight plans, undergoing final medical examinations
and flying in the Shuttle Training Aircraft.
(Reference KSC Shuttle Status 5/30/1998)
- On Thursday, May 28, 1998, preparations to begin the launch
countdown for mission STS-91 at 9:00pm on Saturday are proceeding on
schedule. Installation and checkout of the ordnance on the solid
rocket boosters are complete. Refilling of Discovery's orbiter
maneuvering system oxidizer tank concluded yesterday and
pressurization of the hypergolic system began this morning. Aft main
engine compartment close-outs have resumed today and will conclude
Saturday with aft door installation. The STS-91 flight crew arrives at
KSC Saturday at 12:30 p.m. (Reference KSC Shuttle Status 5/28/1998)
- On Thursday, May 14, 1998, close-outs of Discovery's aft compartment
continued in preparation for Monday's tanking test of the first super
lightweight external tank. Shuttle integrated voltage tests began.
On Wednesday, technicians opened the orbiter's payload bay doors
and completed SPACEHAB tunnel leak checks. SPACEHAB interface
verification testing (IVT) is under way and the AMS IVT is set for
Friday. (Reference KSC Shuttle Status 5/14/1998)
- On Monday, May 11, 1998, replacement of Discovery's master event
controller No. 1 and the change-out of multiplexer demultiplexer No. 4
are complete. Over the weekend, technicians completed work on the
mobile launch platform's gaseous nitrogen system. The payload bay
doors are closed and crew module/SPACEHAB pressure leak checks are
complete. (Reference KSC Shuttle Status 5/11/1998)
- On Saturday, May 2, 1998 Space Shuttle Discovery rolled out of the
Vehicle Assembly Building at 3:26 a.m. and arrived at Pad 39A at about
9:30 a.m. Once at the pad, hotfire testing of Discovery's three
auxiliary power units was completed and launch pad validations
began. On Sunday, the payload was installed into the payload changeout
room. The Rotating Service Structure has been extended to the vehicle
and the orbiter's payload bay doors are slated to be opened later
today. Pad validations continued. The STS-91 flight crew arrived
- at KSC monday evening for the Terminal Countdown Demonstration Test
set for Wednesday and Thursday. (Reference KSC Shuttle Status 05/04/1998)
- On Monday, April 27, 1998, Discovery was transferred from Orbiter
Processing Facility bay 2 to the Vehicle Assembly Building. The
orbiter arrived in the VAB just after 5 p.m. Efforts to mate
Discovery to the new super lightweight external tank in high bay 1
will conclude 4/28/98. The entire Shuttle stack is scheduled for
transport to Pad 39A later this week. NASA managers decided on
Tuesday to move the STS-91 target launch date to June 2. The
additional time will accommodate orbiter processing requirements and
launch preparations at Pad 39A. (Reference KSC Shuttle Status 4/28/1998)
- The new super lightweight external tank, to be used on STS-91,
arrived at KSC s turn basin at about 11 a.m. on Friday 2/6/98. Workers
transported the 154-foot-long improved tank to the Vehicle Assembly
Building (VAB) this afternoon, where it will undergo processing for
flight. The new tank weighs about 7,500 pounds less than the original
ET. (Reference KSC Shuttle Status 2/06/1998)
Orbit:
- Altitude:
- Inclination: 51.60
- Orbits:
- Duration: 9 days, 19 hours, 53 minutes, seconds. (Estimated)
- Distance: miles
Hardware:
- SRB: BIO-91
- SRM: RSRM-66
- ET : SN-96
- MLP :
- SSME-1: SN-2047**A (HPOTP 8025, HPFTP 2232)
- SSME-2: SN-2040* (HPOTP 8017, HPFTP 6113)
- SSME-3: SN-2042* (HPOTP 8019, HPFTP 6011)
Landing:
- KSC June 12, 1998 2:00:17 p.m. EDT. Unofficial main gear touchdown
at MET 9 days, 19 hours, 53 minutes, 57 seconds (2:00 pm EDT). Nose gear
touchdown was 5 seconds later at MET 9 days, 19 hours, 54 minutes, and 2
seconds. Wheel stop occurred at MET 9 days, 19 hours, 55 minutes, and 1
second (2:01 pm EDT).
- Deorbit burn occurred approximately at 12:51 p.m. EDT. A go for
deorbit burn was given at 12:31 p.m.
Mission Highlights:
STS-91 Flight Day 1 Highlights:
STS-91 Flight Day 2 Highlights:
STS-91 Flight Day 3 Highlights:
STS-91 Flight Day 4 Highlights:
STS-91 Flight Day 5 Highlights:
STS-91 Flight Day 6 Highlights:
STS-91 Flight Day 7 Highlights:
STS-91 Flight Day 8 Highlights:
STS-91 Flight Day 9 Highlights:
STS-91 Flight Day 10 Highlights:
STS-91 Flight Day 11 Highlights:
KSC Home Mission Index
Last Mission STS-90
Next Mission STS-95
Last Updated Friday June 29 11:37:03 EDT 2001
Jim Dumoulin (Redacted)
|