|
STS-90 (90)
- Columbia (25)
- Pad 39-B (41)
- 90th Shuttle Mission
- 25th Flight OV-102
- Ascent OMS Burn (2)
- NOTE: Click Here for Countdown Homepage
- Richard A. Searfoss (3), Commander
- Scott D. Altman (1), Pilot
- Richard M. Linnehan DVM (2), Mission Specialist
- Dafydd Rhys Williams MD (1) (CSA), Mission Specialist
- Kathryn P. Hire (1), Mission Specialist
- Dr. Jay C. Buckey (1), Payload Specialist
- Dr. James A. Pawelczyk (1), Payload Specialist
- Alternate Payload SpecialistsD -
- Dr. Alexander W. Dunlap (0), Alternate Payload Specialist
- Dr. Chiaki Mukai (1) (NASDA), Alternate Payload Specialist
Milestones:
- OPF3 -- 12/05/97 (Reference KSC Shuttle Status 12/05/1997)
- VAB3 -- 03/16/98 (Reference KSC Shuttle Status 3/16/1998)
- PAD -- 03/23/98 (Reference KSC Shuttle Status 3/23/1998)
- TCDT -- 03/30/98 (Reference KSC Shuttle Status 3/30/1998)
Payload:
- Neurolab, GAS(G-197, G-467, G-772)
- (Reference KSC Shuttle Status Dec 1997)
- (Reference KSC Shuttle Status Jan 1998)
- (Reference KSC Shuttle Status Feb 1998)
- (Reference KSC Shuttle Status Mar 1998)
- (Reference KSC Shuttle Status Apr 1998)
- (Reference KSC Shuttle Status May 1998)
Mission Objectives:
Click here for Additional Info on STS-90
- Neurolab is a Spacelab module mission focusing on the effects of
microgravity on the nervous system. The goals of Neurolab are to
study basic research questions and to increase the understanding of
the mechanisms responsible for neurological and behavioral changes in
space. Specifically, experiments will study the adaptation of the
vestibular system and space adaptation syndrome, the adaptation of the
central nervous system and the pathways which control the ability to
sense location in the absence of gravity, and the effect of
microgravity on a developing nervous system.
- The mission is a joint venture of six space agencies and seven
U.S. research agencies. Investigator teams from nine countries will
conduct 31 studies in the microgravity environment of space. Other
agencies participating in this mission include six institutes of the
National Institutes of Health, the National Science Foundation, and
the Office of Naval Research, as well as the space agencies of Canada,
France, Germany, and Japan, and the European Space Agency.
Launch:
- Launch April 17, 1998 2:19 p.m. EDT. Launch window was 2 hours, 30
minutes. The crew had breakfast and departed
the Operations and Checkout Building (O&C) for the pad at 11:02 a.m.
The crew arrived at the Pad 39-B and began ingress at 11:18a.m. Hatch closeout was
performed by 12:35 EDT and cabin leak checks were completed at 1:17
EDT. At 1:49pm EDT, the countdown clock came out of the planned hold
at the T-minus 20 minute mark. At 2:10pm EDT, the countdown clock
came out of the T-minus 9 minute mark. Liftoff occured on time at the
start of the launch window. The only ascent problem was with some ice
buildup in the Water Spray Boiler system. Weather officials predicted
a zero percent chance that weather would prohibit launch
activities. The forecast called for few clouds at 3,500 and few clouds
at 25,000 feet; visibility of at least 7 miles; winds from the south
at 12-20 knots; a temperature of 83 degrees F and relative humidity of
55 percent. (Reference KSC Weather History 04/17/1998 1400).
- On Thursday, 4/16/98, at 8:15am, the launch of Space Shuttle
Columbia on mission STS-90 with Neurolab was postponed 24 hours
earlier today due to difficulties with one of two network signal
processors (NSP) on the orbiter. Mission managers first noticed the
problem at about 3 a.m. during normal communications systems
activation prior to tanking operations. As a result, work to load the
external tank with the cryogenic propellants did not begin. The NSPs,
which are located in the orbiter's middeck, format data and voice
communications between the ground and the Space Shuttle. Both
processors are required for launch and landing and are also highly
desirable for on-orbit mission operations. The unit which failed, NSP
No. 2, has at this time been removed and replaced. Testing of the new
unit is scheduled to be completed this evening. The countdown clock
has been reset to the T-11 hour hold position and will remain there
until 11:59 p.m. (Reference KSC Shuttle Status 4/16/1998)
- Middeck animal holding lockers containing 18 pregnant mice and 1514
crickets were removed at the pad. A middeck biotechnology technology
locker was also relocated to provide access to the defective NSP. In
the event the launch cannot be done on 4/17/98, the Neurolab payload
will require a 96 hour scrub turn around to reinstall and resupply
experiments, including 135 snails, 152 rats and 233 fish.
- On Wednesday, 4/15/98, Neurolab late stow activities were completed
early in the morning and closeouts of the spacelab and airlock were
conducted soon afterwards. Activation of Columbia's communications
systems began in the afternoon. RSS rollback was complete by about
8:30pm. Efforts to load the external tank with 500,000 gallons of
liquid oxygen and liquid hydrogen were scheduled to begin at about
5:30 a.m. (Reference KSC Shuttle Status 4/15/1998)
- On Monday, 4/13/98, the launch countdown for mission STS-90 began on
time at 2 a.m. KSC managers are working no major issues at this time
and launch preparations continue on schedule for lift-of on
Thursday. Columbia's aft compartment closeouts are complete and
replacement/reload of mass memory unit No. 1 concluded over the
weekend. Vertical stowage of the flight crew systems is in work and
the first of three Neurolab late stow waves begin this afternoon. The
STS-90 flight crew arrived at KSC's Shuttle Landing Facility at 3:30
p.m. today. They will participate in crew equipment fit checks,
routine medical examinations and fly in the Shuttle Training Aircraft
in the days leading up to launch. (Reference KSC Shuttle Status 4/13/1998)
- On Wednesday, 4/8/98, Columbia's prelaunch preparations continued on
schedule with the launch countdown slated to begin early Monday
morning. Orbiter aft compartment closeouts are proceeding very well
and will conclude Saturday. Payload early stow activities are nearing
completion today in the orbiter's cargo bay. Ordnance installation
begins later today following final inspections of the right forward
booster integrated electronic assembly.
(Reference KSC Shuttle Status 4/08/1998)
- On Friday, 3/27/98, Launch pad validations were completed except for
orbiter midbody umbilical mating activities, slated for the first week
in April. Main engine ball seal leak checks were completed 3/26/98 and
helium signature leak testing occured. Purging of the gaseous nitrogen
(GN2) lines on the mobile launch platform and cleaning of a GN2 panel
continued through the weekend. NASA managers may opt to open
Columbia's payload bay doors on Monday to give technicians access to
two bolts on a getaway special canister. If the work is needed,
technicians will add a washer to each bolt to ensure that the bolts
are properly secured. The doors will be closed again on Tuesday. The
minor unplanned work will not impact the launch date.
(Reference KSC Shuttle Status 3/27/1998)
- On Monday, 3/23/98 at about 7:30 a.m. the Shuttle began its 4.2 mile
trip to launch Pad 39B atop th crawler transporter and arrived at Pad 39B
at about 3:20 p.m. At about 7 p.m., the Rotating Service Structure (RSS) was
extended around the Shuttle (Reference KSC Shuttle Status 3/24/1998)
- On Friday, March 20, 1998, Columbia's Shuttle Interface Test was
successfully concluded. (Reference KSC Shuttle Status 3/23/1998)
- On Monday, March 16, 1998, Columbia rolled over to the VAB.
(Reference KSC Shuttle Status 3/16/1998)
- On Thursday, March 12, 1998, work on Columbia's right inboard elevon
was completed and both forward and aft compartment close-outs were in
work. Tomorrow, technicians will complete work to install the aft
doors. Aft compartment structural leak tests will follow.
(Reference KSC Shuttle Status 3/12/1998)
- On Monday, 3/2/98, The Neurolab transfer tunnel has been
mechanically and electrically mated and the tunnel interface
verification test was completed on Friday. Space Shuttle main engine
close-out operations and leak checks are complete. Main engine heat
shields are being installed and a landing gear functional test is
scheduled for today. In the Vehicle Assembly Building, the external
tank was successfully mated to the solid rocket boosters on
Thursday. (Reference KSC Shuttle Status 3/02/1998)
- On 2/26/98, work to install the Space Shuttle Main Engines (SSME's)
were complete. The STS-90 crew participated in the crew equipment
and interface test (CEIT) and a sharp edge inspection of the orbiter's
crew module and Neurolab. (Reference KSC Shuttle Status 2/26/1998)
- On Thursday, 2/5/98, installation of Columbia's airlock hatch "D"
was completed. The hatch provides access from the tunnel adapter to
the Spacelab transfer tunnel. On Friday, 2/6/98, functional tests on
Columbia's airlock hatch "D" and inspections of micrometeorite hits on
the orbiter radiator and checklife support system were completed. Aft
compartment closeouts and payload premate testing continued. Technicians
proceeded with main engine heat shield rework efforts. The Neurolab
payload is scheduled to arrive at the OPF on Wednesday (2/11/98) for
installation into the orbit's cargo bay and the Shuttle main engines
will be installed on Thursday. (Reference KSC Shuttle Status 2/06/1998)
- On Monday, February 2, 1998, replacement of a relief valve on Columbia's
auxiliary power unit No. 2 and water spray boiler checkout were
completed. Leak checks on the Spacelab water line are also completed
and work on payload bay flood light No. 3 continued. Tunnel adapter
flow rate leak testing and airlock ducting reconfiguration were also
in work. (Reference KSC Shuttle Status 2/02/1998)
- On Monday, January 12, 1998 Technicians completed removal of
Columbia's window No. 6 yesterday and installed the new window on
1/13/98. Replacement of floodlights No. 1 and No. 5, in the orbiter's
payload bay was in work as well as aft flight deck reconfiguration.
Fuel cell voltage tests and checks of the flash evaporator system
were also scheduled. (Reference KSC Shuttle Status 1/13/1998)
- On Monday, January 5, 1998, Shuttle Columbia's payload bay doors
were opened yesterday to accommodate Ku band antenna testing yesterday
afternoon. The orbiter's nose and main landing gear tires were also
installed yesterday. Orbiter maneuvering system testing and
replacement of fuel cells No. 1 and 3 are in work. Window polishing
efforts begin tomorrow and inspections of the forward reaction control
system are scheduled for Friday 1/9/98.
(Reference KSC Shuttle Status 1/08/1998<
- Orbiter Thermal Protection System (TPS) Tile damage was
found on Columbia following its inspection after STS-87 landed
on 12/5/97. 99 tile removals are planned with 40 tile removals
under evaluation.
-
Orbit:
- Altitude:150 nautical miles
- Inclination: 39 degrees
- Orbits: 256
- Duration: 15 days, 21 hours, 50 minutes, 58 seconds.
- Distance: miles
Hardware:
- SRB: BIO-94
- SRM: RSRM-65
- ET : SN-91
- MLP : 2
- SSME-1: SN-2041 (HPOTP 8013, HPFTP 6110)
- SSME-2: SN-2032 (HPOTP 4211, HPFTP 2128)
- SSME-3: SN-2012 (HPOTP 6209, HPFTP 4117)
Landing:
- KSC May 3, 1998 12:09 p.m. EDT Runway 33. Landing Groundtracks for
the 1st KSC landing opportunity took the shuttle over southern
Mississippi and Alabama. Sonic booms heard at KSC at 12:05pm EST as
Columbia approached. Main Gear Touchdown 15 days 21 hours 49 minutes
59 seconds. (12:08:59 EST) Nose Gear Touchdown 15 days 21 hours
50 minutes 13 seconds. (12:09:13 EST). Wheels Stop 15 days 21 hours
50 minutes 58 seconds. (12:09:58 EST).
- Meteorologists are forecasting favorable conditions at the Kennedy
Space Center on Sunday for a landing at 12:09 a.m. EDT on the 1st of
two KSC landing opportunities. At 10:28am EDT, APU Prestart was
complete.
Mission Highlights:
STS-90 Flight Day 1 Highlights:
STS-90 Flight Day 2 Highlights:
STS-90 Flight Day 3 Highlights:
STS-90 Flight Day 4 Highlights:
STS-90 Flight Day 5 Highlights:
STS-90 Flight Day 6 Highlights:
STS-90 Flight Day 7 Highlights:
STS-90 Flight Day 8 Highlights:
STS-90 Flight Day 9 Highlights:
STS-90 Flight Day 10 Highlights:
STS-90 Flight Day 11 Highlights:
STS-90 Flight Day 12 Highlights:
STS-90 Flight Day 13 Highlights:
STS-90 Flight Day 14 Highlights:
STS-90 Flight Day 15 Highlights:
STS-90 Flight Day 16 Highlights:
STS-90 Flight Day 17 Highlights:
KSC Home Mission Index
Last Mission STS-89
Next Mission STS-91
Last Updated Friday June 29 11:37:03 EDT 2001
Jim Dumoulin (Redacted)
|