Challenger (STA-099, OV-99)

Background

Upgrades and Features

Construction Milestones (MPTA-098)

07/26/72 Contract Award
06/24/75 Start structural assembly of aft-fuselage
07/12/76 Start of Final Assembly
05/27/77 Completed Final Assembly
04/21/78 Flight Readiness Firing

Construction Milestones (STA-099)

07/26/72 Contract Award
11/21/75 Start structural assembly of Crew Module
06/14/76 Start structural assembly of aft-fuselage
03/16/77 Wings arrive at Palmdale from Grumman
09/30/77 Start of Final Assembly
02/10/78 Completed Final Assembly
02/14/78 Rollout from Palmdale

Construction Milestones (OV-099)

01/05/79 Contract Award
01/28/79 Start structural assembly of Crew Module
06/14/76 Start structural assembly of aft-fuselage
03/16/77 Wings arrive at Palmdale from Grumman
11/03/80 Start of Final Assembly
10/23/81 Completed Final Assembly
06/30/82 Rollout from Palmdale
07/01/82 Overland transport from Palmdale to Edwards
07/05/82 Delivery to Kennedy Space Center
12/19/82 Flight Readiness Firing
04/04/83 First Flight (STS-6)

Challenger's Flights to date:

01. STS-6 (04/04/83)
02. STS-7 (06/18/83)
03. STS-8 (08/30/83)
04. 41-B (02/03/84)
05. 41-C (04/06/84)
06. 41-G (10/05/84)
07. 51-B (04/29/85)
08. 51-F (07/29/85)
09. 61-A (10/30/85)
10. 51-L (1/28/86 - Crew and vehicle lost during launch)

Challenger Flight Log:

10 flights
987 orbits
69 days in space