|
STS-99 (97)
- Endeavour (14)
- Pad 39-A (68)
- 97th Shuttle Mission
- 14th Flight OV-105
- KSC Landing (50)
- NOTE: Click Here for Countdown Homepage
- Kevin R. Kregel (4), Mission Commander
- Dominic L. Pudwill Gorie (2), Pilot
- Janet L. Kavandi (2), Mission Specialist
- Janice E. Voss (5), Mission Specialist
- Mamoru Mohri (2), Mission Specialist (NASDA)
- Gerhard P.J. Thiele (1), Mission Specialist
Milestones:
- OPF -- 12/15/98 (Reference KSC Shuttle Status 12/15/1998)
- VAB -- 7/11/99 (Reference KSC Shuttle Status 7/16/1999)
- PAD -- 12/13/99 (Reference KSC Shuttle Status 12/13/1999)
Payload:
- SRTM,EarthKAM
Mission Objectives:
Click here for Additional Info on STS-99
- The Shuttle Radar Topography Mission (SRTM) is an international
project spearheaded by the National Imagery and Mapping Agency and
NASA, with participation of the German Aerospace Center DLR. Its
objective is to obtain the most complete high-resolution digital
topographic database of the Earth. SRTM consists of a specially
modified radar system that will fly onboard the space shuttle during
its 11-day mission. This radar system will gather data that will
produce unrivaled 3-D images of the Earth's surface.
- SRTM uses C-band and X-band interferometric synthetic aperture
radars (IFSARs) to acquire topographic data of Earth's land mass
(between 600N and 560S). It produces digital topographic map products
which meet Interferometric Terrain Height Data (ITHD)-2 specifications
(30 meter x 30 meter spatial sampling with 16 meter absolute vertical
height accuracy, 10 meter relative vertical height accuracy and 20
meter absolute horizontal circular accuracy).
- The result of the Shuttle Radar Topography Mission could be close to
1 trillion measurements of the Earth's topography. Besides
contributing to the production of better maps, these measurements
could lead to improved water drainage modeling, more realistic flight
simulators, better locations for cell phone towers, and enhanced
navigation safety.
Launch:
- February 11, 2000. 12:43 pm EST (17:43 UTC) Launch window was 2 hours and 10 min.
- On Friday, February 11, 2000, Fueling of the external tank began at
3:49 am (EST) and entered into stable replenish mode at 6:37 a.m. At
8:02 am EST, the crew had their prelaunch breakfast and prepared to
enter their launch and entry suits. At 9:09 am EST, the countdown
clock came out of the hold at the T-minus 3 hour mark. At 9:15 am
(14:15 UTC), the crew departed the Operations and Checkout Building
(O&C) for Launch Pad 39A. By 9:30 am the crew was in the white room
and began ingress into the orbiter. By 10:57 am the hatch was closed
and locked for flight. The countdown clock was held at the T-minus 9
minute mark to resolve 3 minor technical issues relating to the cabin
leak check supply pressure, a hydraulic recirculation pump and a L2
manifold tank heater. The count picked back up and the Orbiter Access
Arm (OAA) was retracted at 12:36pm. The gaseous Oxygen vent arm was
retracted at 12:41pm. A go for auto sequence start was given at the
T-minus 20 second mark. Liftoff occured 12:43 (UTC 17:43).
- On Thursday, February 10, 2000, Preparation continues on schedule
today for the launch of Space Shuttle Endeavour this Friday at 12:30
p.m. EST. Replacement of the global positioning system box located
inside Endeavour's crew module concluded yesterday and tests of the
new unit are complete. The orbiter's onboard storage tanks were loaded
with cryogenic reactants last night and no significant issues are
being worked by the KSC launch team at this time. Today,Endeavour's
three main engines will be prepared for propellant loading
operations. The orbiter's communication systems will be activated this
morning and this afternoon flight crew equipment late stow operations
begin. The Rotating Service Structure will move to the park position
at about 6:30 p.m., revealing the entire Shuttle for the first time
since the last launch attempt. (Reference KSC Shuttle Status 2/10/2000)
- On Wednesday, February 9, 2000, The launch countdown for mission
STS-99 began on time yesterday at 5:30 p.m. EST, and final preparation
for Friday's launch continues on schedule at Launch Pad 39A. A global
positioning system box located inside Endeavour's crew module will be
replaced following a failed self test this morning. Replacement
efforts begin this evening and will not impact the launch date. The
component supports SRTM payload operations in flight. This morning,
routine tests of Endeavour's pyrotechnic initiator controllers
confirmed that the safe and arm device indicator located in the left
hand solid rocket booster's forward skirt is functioning as expected
and is ready for launch. This was a confidence test for Shuttle
engineers who yesterday completed inspections of a cable that supports
the device. Inspections revealed only superficial scuffing to exterior
tape and confirmed that the cable was intact. (Reference KSC Shuttle Status 2/09/2000)
- On Tuesday, February 1, 2000, mission managers decided to delay the
launch until no earlier than February 9, 2000 to give the launch team
time to swap out Endeavour's Enhanced Master Events Controller (EMEC)
#2 located in the orbiter's aft compartment.. A launch was last
delayed August 29, 1984 onDiscovery's STS 41-D flight due to a MEC.
Engineers have not been able to reproduce the problem and are
continuing their evaluation. Preliminary analysis and testing
indicates a possible hardware problem within the unit. The unit weighs
65 pounds, is approximately 20 inches long, 13 inches wide and 8
inches tall. A spare is available at KSC and today workers are testing
the replacement EMEC unit. (Reference KSC Shuttle Status 2/01/2000)
- On Monday, January 31, 2000, tanking operations began at 4:10am EST
and transititioned to stable replenish mode at 7:04 am EST. At around
8am EST a team was sent to the launch pad to troubleshoot a redundant
power supply on the LH2 recirculation pump on the mobile launch
platform. The ice inspection team was also at the pad inspecting the
vehicle. The crew ate their preflight meal (Red Team breakfast and
Blue Team lunch) and at 9:10am EST, suited up for flight. At 9:34 am
EST the crew departed the Operations and Checkout Building for Launch
Pad 39A. At 11:08 am EST, the hatch was closed and locked for flight.
The countdown clock counted down to the T-minus 20 minute mark and was
kept in a hold condition due to weather conditions. The launch team
also investigatigated a potential problem with the onboard Master
Events Controller (MEC) #2 Built In Test Equipment (BITE). The
problem did not reoccur during additional testing. At 1:58pm EST,
(18:58 UTC) NTD gave the go to pickup the count and countdown to
the T-minus 9 minute mark and hold pending weather. At 2:08pm EST,
the call was made to scrub due to weather constraints and enter into
at 24 hour scrub turnaround. The new launch date was tentatively set for
Tuesday, February 1, 2000 at 12:44pm.EST. Over the night,
engineering teams will evaluate data from the Master Events Controller.
- On Thursday, January 27, 2000, At Launch Pad 39A, work continues in
preparation for Monday's launch of Shuttle Endeavour. This week,
workers completed Shuttle ordnance installation and the aft
compartment doors were installed yesterday. Endeavour's reaction
control and maneuvering systems have been pressurized for flight and
early flight crew equipment stowage is complete. Today at about noon,
the STS-99 flight crew arrived at KSC to make final preparation for
their upcoming flight. Over the next few days, crew members will
review mission procedures, conduct test flights in the Shuttle
Training Aircraft and undergo routine preflight medical exams. The
launch countdown begins tomorrow at 5:30 p.m. and will be conducted in
Control Room No. 3 in KSC's Launch Control Center.
(Reference KSC Shuttle Status 1/27/2000)
- On Wednesday, January 26, 2000, Aft compartment close-outs are
complete. Replacement of the four payload bay camera assemblies is
complete and retesting concluded today. While the payload bay doors
are open, workers will clean the optics on the SRTM Attitude and Orbit
Determination Assembly (AODA). Door closure is slated to occur
tonight. Endeavour remains in the standard cold weather configuration
with the reaction control system heaters powered up. The flight crew
arrives at KSC tomorrow at about noon and the countdown clock starts
Friday at 5:30 p.m. (Reference KSC Shuttle Status 1/26/2000)
- On Monday, January 24, 2000, Over the weekend, engineers determined that
four camera mounts in Endeavour's payload bay will be replaced with no
schedule impact. Tuesday morning, the orbiter's payload bay will be
opened and workers will remove and replace two camera assemblies from
the forward bulkhead and two camera assemblies from the aft
bulkhead. Analysis showed that the camera mounts were slightly
yielding to the camera's weight. A strengthening modification has been
implemented on the replacement units. (Reference KSC Shuttle Status 1/24/2000)
-
- On Wednesday, January 5, 2000, The launch team is conducting a
standard launch countdown simulation today in KSC's Launch Control
Center. At the launch pad this week, workers are preparing to load
propellant into Endeavour's onboard storage tanks. On Friday,
engineers will conduct the Shuttle helium signature leak test. Leak
checks on the orbiter's midbody umbilical unit are scheduled to occur
next Wednesday. Terminal Countdown Demonstration Test activities with
the flight crew are slated to occur Jan. 13 and 14.
- (Reference KSC Shuttle Status 1/05/2000)
- On Monday, December 13, 1999 Space Shuttle Endeavour rolled out of
the Vehicle Assembly Building today at 7 a.m., headed toward Launch
Pad 39A. Once at the pad, workers will begin routine launch pad
validations. All three auxiliary power units will be hot fire tested
tomorrow. The remainder of the STS-99 prelaunch work schedule is being
reviewed due to the recent engine replacement and in order to
accommodate STS-103 processing efforts. (Reference KSC Shuttle Status 12/13/1999)
- On Wednesday, December 1, 1999 Workers in the OPF have completed
wiring close-outs on OrbiterEndeavour and the payload bay doors were
closed last night. Preparations are under way for Endeavour to roll to
the Vehicle Assembly Building Thursday at about 10 a.m. The orbiter
will be mated to the external tank and solid rocket boosters in VAB
high bay 1Thursday night and managers plan to transfer the Space
Shuttle to Launch Pad 39A Dec. 7.
(Reference KSC Shuttle Status 12/01/1999)
- On Thursday, October 7, 1999, with wiring inspections and repairs
of Discovery andEndeavour nearing completion and similar work beginning
on Atlantis, Shuttle program managers set new planning target launch
dates for the next three Space Shuttle missions.
(<>Reference KSC Shuttle Status 10/7/1999)
- On Thursday, September 2, 1999, payload engineers have determined
that the bent freon line associated with the SRTM payload will be
repaired with a brace and replacing the line will not be
necessary. The bent line was reported earlier this month by a
technician working in that area. The freon line is part of a cooling
system for some of the SRTM electronics. (Reference KSC Shuttle Status 9/2/1999)
- On Thursday, August 19, 1999, workers removed the Shuttle Radar
Topography Mission payload from Endeavour's payload bay and
established access to the orbiter's midbody for planned wiring
inspections. Inspections are expected to begin this weekend. With
wiring inspection and maintenance plans now in place, implementation
efforts are in progress across the Shuttle fleet. Shuttle managers
are reviewing several manifest options this week and could establish
the new target launch dates for 1999 as early as next week. Engineers
must first define the time that will be needed to complete the
fleet-wide wiring maintenance effort. Shuttle Endeavour currently
remains slated for launch in early October.
(Reference KSC Shuttle Status 8/19/1999)
- On Thursday, August 12, 1999 Shuttle managers decided to delay the
rollout of Shuttle Endeavour from OPF bay 2 to the Vehicle Assembly
Building to conduct extensive wiring inspections and preventative wire
maintenance in the orbiter's payload bay. In depth evaluation of
payload bay wiring aboard orbiters Columbia andAtlantis revealed the
potential for damaged wire to exist in Endeavour's payload bay. The
additional work will delay the STS-99 launch to at least early
October. Tomorrow, workers will begin preparations to remove the SRTM
payload from Endeavour's payload bay to gain access to the lower cable
trays that run the length of the orbiter's midbody. Once access is
established, Shuttle engineers and technicians will begin necessary
inspection and mitigation efforts. The impact of this delay and the
unplanned wiring work needed on the rest of the Shuttle fleet is being
assessed. (Reference KSC Shuttle Status 8/12/1999)
- On Friday, July 16, 1999 Technicians have completed functional tests
on Endeavour's landing gear. Payload bay close-outs continue and
potable water servicing is ongoing. Leak checks of the crew cabin and
external airlock are scheduled today. Preparations are under way to
receive the SRTM payload into the OPF and then install it into the
orbiter's payload bay next Tuesday. The orbiter/payload interface
verification test begins next week. (Reference KSC Shuttle Status 7/16/1999)
- On Tuesday, April 20, 1999, Modifications to Endeavour's radiator
isolation valve are under way. Leak repair on the cold plate for the
orbiter's power converter unit is ongoing. Orbiter docking system
harness installation is in work and external airlock installation
efforts conclude May 6. (Reference KSC Shuttle Status 4/20/1999)
- On Thursday, March 18, 1999, Installation of Endeavour's three
auxiliary power units (APU) concludes today when technicians install
APU No. 2. Valve modifications on freon coolant loop No. 1 continue to
go well. Next week, fuel cells No. 1 and No. 2 are being replaced and
preparations to replace the left-hand orbital maneuvering system
engine are ongoing. (Reference KSC Shuttle Status 3/18/1999)
- On Thursday, February 25, 1999, modifications of Endeavour's freon
coolant loop No. 1 continued to go well, with replacement of the left
hand radiators now complete. The orbiter's forward reaction control
system (RCS) will arrive in the OPF today for installation inside the
orbiter's nose on Saturday. (Reference KSC Shuttle Status 2/25/1999)
Orbit:
- Altitude: 126nm
- Inclination: 57
- Orbits: 181
- Duration: 11 days, 5 hours, 39 minutes 41 seconds.
- Distance: 4 million 64 thousand miles
Hardware:
- SRB:
- SRM:
- ET :
- MLP : 3
- SSME-1: SN-
- SSME-2: SN-
- SSME-3: SN-
Landing:
- KSC Runway 33 Feb. 22, 2000 6:23 p.m. EST. At 5pm EST, a go was given
for the deorbit burn for KSC's 2nd landing opportunity and the deorbit burn occured
at 5:24 p.m EST. Sonic booms heard at 6:18 p.m. EST at KSC 3.5 minutes before
touchdown. Main Gear Touchdown at MET 11 days 5 hours 38 min (18:22:23:174 EST).
- Nose Gear touchdown at MET 11 days 5 hours 39 minutes (18:22:34:569 EST).
- Wheel Stop at MET 11 days 5 hours 39 minutes 41 seconds (18:23:25:529 EST).
- The 1st landing opportunity for KSC at 4:50 p.m. EST was waived off
due to weather concerns. A second opportunity to land in Florida was
available with a touchdown at 5:22 p.m. CST. Endeavour could have also
landed at Edwards Air Force Base, California, with a touchdown at 6:48
p.m. CST. Flight controllers closely monitored the weather at
the Kennedy Space Center.and at Edwards Air Force Base. High winds and
possible cloud cover were forecast for Kennedy that could have prohibited a
landing there. The forecast for Edwards called for acceptable landing
weather.
- To land on the first opportunity to Florida, Endeavour would have had to fire
its engines to begin its descent at 2:53 p.m. CST. For the second
Florida landing opportunity, Endeavour fired its engines at 4:24
p.m. to leave orbit. For a landing in California, Endeavour would have
had to fire its engines at 5:51 p.m. CST.
Mission Highlights:
STS-99 Flight Day 1 Highlights:
STS-99 Flight Day 2 Highlights:
STS-99 Flight Day 3 Highlights:
STS-99 Flight Day 4 Highlights:
STS-99 Flight Day 5 Highlights:
STS-99 Flight Day 6 Highlights:
STS-99 Flight Day 7 Highlights:
STS-99 Flight Day 8 Highlights:
STS-99 Flight Day 9 Highlights:
STS-99 Flight Day 10 Highlights:
STS-99 Flight Day 11 Highlights:
STS-99 Flight Day 12 Highlights:
KSC Home Mission Index
Last Mission STS-103
Next Mission STS-101
Last Updated Friday June 29 11:37:08 EDT 2001
Jim Dumoulin (Redacted)
|