STS-98 (102)
- Atlantis (23)
- Pad 39-A (71)
- 102nd Shuttle Mission
- 23rd Flight OV-104
- Rollback (14)
- EAFB Landing (47)
- NOTE: Click Here for Countdown Homepage
Crew:
- Kenneth D. Cockrell (4), Commander
- Mark L. Polansky (1), Pilot
- Robert L. Curbeam (2), Mission Specialist
- Thomas D. Jones (4), Mission Specialist
- Marsha S. Ivins (5), Mission Specialist
Milestones:
- OPF -- 09/20/00 (Reference KSC Shuttle Status 9/20/2000)
- VAB -- 12/04/00 (Reference KSC Shuttle Status 12/04/2000)
- PAD -- 01/02/01 (Reference KSC Shuttle Status 1/02/2001)
- Rollback
- VAB -- 01/19/01 (Reference KSC Shuttle Status 1/15/2001)
- PAD -- 01/26/01 (Reference KSC Shuttle Status 1/25/2001)
Payload:
- 7th Space Station Assembly Flight ISS-07-5A (US Lab), ORU, PDGF
Mission Objectives:
Click here for Additional Info on STS-98
- The crew will continue the task of building and enhancing the
International Space Station by delivering the U.S. laboratory
module. The Shuttle will spend six days docked to the station while
the laboratory is attached and three spacewalks are conducted to
complete its assembly. The STS-98 mission will occur while the first
station crew is aboard the new spacecraft.
Launch:
- February 7, 2001, 6:13 p.m. EST KSC Launch window was 4 minutes, 48
seconds.
-
- On Wednesday, February 7, 2001, Loading of the external tank was
scheduled to begin at 9:16 a.m. but began early at 8:45 a.m. and was
in stable replenish mode by 12:30 p.m. Forecasters initially
indicated a 10 percent chance of KSC weather violating launch commit
criteria on Wednesday but upgraded that to a 100 percent chance of
favorable weather. The only issues worked during the countdown were
concerns over weather at the TAL sites in Spain and Morocco. At 2:30
p.m, the crew left the O&C building and proceeded to Pad 39-A. By
shortly after 4:00pm, the crew hatch was closed and locked for flight.
At 5:49 p.m. the launch team discussed concerns about an irregular
voltage measurement on one of Atlantis's MDM's but decided it was a
sensor issue. Launch occured 2 minutes after the planned liftoff
time.
- On Tuesday, February 6, 2001, the KSC launch team proceed on schedule
with STS-98 launch preparations. Monday night, workers loaded
cryogenic reactants into Space Shuttle Atlantis' onboard storage tanks
and Shuttle pyrotechnic tests concluded that afternoon. At the launch
pad, the orbiter's midbody umbilical unit was demated and the sound
suppression system water tank was filled.
(Reference KSC Shuttle Status 2/06/2001)
- On Sunday, February 5, 2001 the flight crew arrived at KSC at 1:43
p.m EST and the countdown clock began at 10 p.m EST (03:00 GMT) at the
T-minus 43 hour mark. Sunday morning, workers replaced one of the
three space suits aboard Atlantis.
-
- On Friday, 1/26/2001, Space Shuttle Atlantis rolled out of the
Vehicle Assembly Building (VAB) at 6:48 a.m. and arrived at Launch Pad
39A at 12:44 p.m. (Reference KSC Shuttle Status 1/26/2001)
- On Thursday, 1/25/2001, Shuttle managers today announced Feb. 7 as
the target launch date for Space Shuttle Atlantis on mission STS-98.
The previous launch date was 2/6/2001 at 6:37 p.m. The new date
accommodates scheduled launch activities on the Eastern Range and
better supports a desire to rendezvous with the orbiting International
Space Station on flight day 3. (Reference KSC Shuttle Status 1/25/2001)
- On Monday, 1/22/2001, Over the weekend, technicians successfully
completed continuity "wiggle" tests on the systems tunnel cables
located in both STS-98 solid rocket boosters. Workers began collecting
X-ray images of the cables Sunday and concluded that effort at 2:30
a.m. today. Analysis of the X-ray images confirmed that the cables
have no physical damage. (Reference KSC Shuttle Status 1/22/2001)
-
- On Monday, 1/15/2001, After additional testing and analysis of Solid
Rocket Booster cables throughout the Shuttle fleet, Shuttle Program
officials decided late today to return Atlantis to the Vehicle
Assembly Building at the Kennedy Space Center.to conduct further
inspections. Because of the uncertainty involving the integrity of the SRB
cables, Shuttle Program Manager Ron Dittemore ordered Atlantis to be
rolled back to the Vehicle Assembly Building later this week for more
inspections. The rollback is scheduled to take place Friday.
- The rollback was ordered prior to the planned start of the countdown
early Tuesday for Atlantis' scheduled launch January 19 to deliver the
U.S. Laboratory Destiny to the International Space Station. The launch
will be delayed until no earlier than February 6. Atlantis' five
astronauts were informed of the rollback decision prior to their
departure from Ellington Field in Houston for KSC. They will come out
of quarantine to resume training for their mission.
- As a result of the rollback decision, Destiny will be removed from
Atlantis' payload bay Thursday and will remain in the payload change
out room at Launch Pad 39-A. Pending the results of the cable
inspections, which will begin this weekend, Atlantis could return to
the launch pad around January 25 to resume pre-launch preparations.
Atlantis' launch delay will have some impact on the scheduled March 1
launch of Discovery on the STS-102 / 5A.1 mission to the International
Space Station. Shuttle program officials will be assessing the
potential launch impact over the next few weeks.
- (Reference KSC Shuttle Status 1/15/2001)
- On Tuesday, 1/2/2001, the Space Shuttle Atlantis began its move to
Launch Pad 39A at about 8:30 a.m., but an hour later stopped on the
crawler path so engineers could troubleshoot a failed computer
processor on th crawler transporter. Troubleshooting efforts were
unsuccessful, so managers decided to roll Atlantis back into VAB high
bay 3 using a secondary computer processor. Managers plan to use KSC
' crawler transporter No. 2 tomorrow instead of the trouble crawler
transporter No. 1. First motion to the launch pad is now expected
between 9 a.m. and 10 a.m. Wednesday. Managers are assessing the
impact of this unexpected delay on the remainder of the processing
schedule. (Reference KSC Shuttle Status 1/02/2001)
- Prior to the holidays, Shuttle managers completed an extensive evaluation of
the STS-98 solid rocket booster ordnance cables and determined that they are
ready for flight. After thorough inspection, X-ray analysis and functional
testing, engineers identified minor damage to an outer layer of woven metal
shielding on a cable associated with the left-hand booster's lower
attachment strut. The damaged area was repaired and retested. Subsequent
analysis confirmed the cable's flight readiness. (Reference KSC Shuttle Status 1/02/2001)
-
Orbit:
- Altitude: 173 nm
- Inclination: 51.6
- Orbits: 202
- Duration: 12 days, 21 hours, 21 minutes, 00 seconds.
- Distance: 5.3 million miles
Hardware:
- SRB:
- SRM:
- ET : SN-103
- MLP : 2
- SSME-1: SN-
- SSME-2: SN-
- SSME-3: SN-
Landing:
- Feb 20, 2001 at 3:33 p.m EST Edwards AFB Runway 22
- Main Gear touchdown: 12 Days 21 Hours 20 minutes 03 seconds (12:33:05 PST)
- Nose Gear touchdown: 12 Days 21 Hours 20 minutes 15 seconds (12:33:17 PST)
- Wheels Stop: 12 Days 21 Hours 21 minutes 00 seconds (12:34:02 PST)
- Landing opportunities on February 18 and February 19, 2001 were
waived off due to weather concerns. The two KSC Landing opportunities
for February 20, 2001 were also waived off. The shuttle landed on the
1st landing opportunity for Edwards Air Force Base in California.
- There were two landing opportunities at the Kennedy Space Center.on
Tuesday, February 20 with the first opportunity calling for the firing
of Atlantis' braking rockets on orbit 200 at 10:20 a.m. Central time,
resulting in a landing at the Cape at 11:27 a.m. Central time. The
second opportunity would have begun with the deorbit burn maneuver on orbit
201 at 11:56 a.m. Central time and a landing at the Kennedy Space
Center at 1:02 p.m. Central time. Both were waived off due to
weather concerns.
- Two landing opportunities also are available on the next two orbits
at Edwards. The first of the Edwards' opportunities would call for the
deorbit burn at 1:27 p.m. Central time and a landing at 2:33
p.m. Central time. The final opportunity of the day on Tuesday for
Edwards would involve a deorbit burn at 3:04 p.m. Central time and a
landing at 4:09 p.m. Central time. The weather at Edwards is also
expected to be better, with a chance of broken cloud decks and lighter
winds than were observed today. Landing support will also be called
up for the White Sands Space Harbor at Northrup Strip in New Mexico,
which has three landing opportunities available, although all efforts
will be made to try to bring Atlantis home in either Florida or
California.
Mission Highlights:
STS-98 Flight Day 1 Highlights:
STS-98 Flight Day 2 Highlights:
STS-98 Flight Day 3 Highlights:
STS-98 Flight Day 4 Highlights:
STS-98 Flight Day 5 Highlights:
STS-98 Flight Day 6 Highlights:
STS-98 Flight Day 7 Highlights:
STS-98 Flight Day 8 Highlights:
STS-98 Flight Day 9 Highlights:
STS-98 Flight Day 10 Highlights:
STS-98 Flight Day 11 Highlights:
STS-98 Flight Day 12 Highlights:
STS-98 Flight Day 13 Highlights:
STS-98 Flight Day 14 Highlights:
KSC Home Mission Index
Last Mission STS-97
Next Mission STS-102
Last Updated Wednesday July 25 06:41:43 EDT 2001
Jim Dumoulin (Redacted)
|