|
STS-82 (82)
- Discovery (22)
- Pad 39-A (59)
- 82nd Shuttle Mission
- 22th Flight OV-103
- Night Launch (17)
- KSC Landing
- 9th Night Landing
- NOTE: Click Here for Countdown Homepage
- Kenneth D. Bowersox (4), - Commander
- Scott J. Horowitz (2), Pilot
- Mark C. Lee (4), Mission Specialist
- Steven A. Hawley (4), Mission Specialist
- Gregory J. Harbaugh (4), Mission Specialist
- Steven L. Smith (2), Mission Specialist
- Joseph R. Tanner (2), Mission Specialist
Milestones:
- OPF -- 06/30/96 (Reference KSC Shuttle Status 7/01/1996)
- VAB -- 01/11/97 (Reference KSC Shuttle Status 1/09/1997)
- PAD -- 01/17/97 (Reference KSC Shuttle Status 1/17/1997)
- TCDT -- 01/22/97 (Reference KSC Shuttle Status 1/22/1997)
- FRR -- 01/30/97 (Reference KSC Shuttle Status 1/30/1997)
- LAUNCH -- 02/11/97 (Reference KSC Shuttle Status 2/11/1997)
Payload:
- Hubble Servicing Mission 2
- (Reference KSC Shuttle Status Jan 1997)
- (Reference KSC Shuttle Status Feb 1997)
Mission Objectives:
Click here for Press Kit Click here for Additional Info on STS-82
- Service the Hubble Space Telescope. The STS-82 mission is the
second in a series of planned servicing missions to the orbiting
Hubble Space Telescope (ST). HST was placed in orbit on April 24,
1990 by the Space Shuttle Discovery on STS-31. The first servicing
mission was done by Space Shuttle Endeavour on STS-61. Work performed
on the telescope will significantly upgrade the scientific
capabilities of the HST and keep the telescope functioning smoothly
until the next scheduled servicing missions in 1999 and 2002.
- Starting on the third day of the mission, the seven-member crew will
conduct at least four spacewalks (also called Extravehicular
Activities or EVAs) to remove two older instruments and install two
new astronomy instruments, as well as other servicing tasks. The two
older instruments being replaced are the Goddard High Resolution
Spectrometer and the Faint Object Spectrograph. Replacing these
instruments are the Space Telescope Imaging Spectrograph (STIS) and
the Near Infrared Camera and Multi-Object Spectrometer (NICMOS).
HST's current complement of science instruments includes two cameras,
two spectrographs, and fine guidance sensors.
- In addition to installing the new instruments, astronauts will
replace other existing hardware with upgrades and spares. Hubble will
get a refurbished Fine Guidance Sensor, an optical device that is used
on HST to provide pointing information for the spacecraft and is used
as a scientific instrument for astrometric science. The Solid State
Recorder (SSR) will replace one of HST's current reel-to-reel tape
recorders. The SSR provides much more flexibility than a reel-to-reel
recorder and can store ten times more data. One of Hubble's four
Reaction Wheel Assemblies (RWA) will be replaced with a refurbished
spare. The RWA is part of Hubble's Pointing Control Subsystem. The
RWAs use spin momentum to move the telescope into position. The
wheels also maintain the spacecraft in a stable position. The wheel
axes are oriented so that the telescope can provide science with only
three wheels operating, if required.
Launch:
- Launch February 11, 1997 3:55:17 am. Window was 65 minutes.
The exact window was announced a few hours before launch and adjusted
at the T-9 minute mark based on the final computation of the location
of the Hubble Space Telescope (HST). In Firing Room 3, of the
Launch Control Center (LCC), a final poll of the launch team and the
Mission Management Team was conducted and the countdown clock picked
up at the T-9 minute mark at 3:47am EST. The Orbiter Access Arm (OAA)
was retracted at T-7 minute 21 seconds (3:50am EST) and a go was
given for APU prestart at 3:50am EST. The APU's were started at the
T-5 minute mark and the flight crew reported 3 good APU's. Discovery's
aero surfaces were sequenced and the three Space Shuttle Main Engines (SSME's)
were moved into launch position. Launch occured exactly on schedule.
Solid Rocket Boosters (SRB's) were seperated at 2 minutes 2 seconds with
Discovery at an altitude 35nm and a distance of 40 miles from launch site.
- The launch countdown was conducted with minimal problems. Loading
of the cryogenic reactants into the external tank began at 8:30
p.m. EST on February 10, 1997. Tanking was delayed about 1 1/2 hours
in order to send a contingency team into the Mobile Launcher Platform
(MLP) at the pad to assess the integrity of the gaseous nitrogen purge
system. This was done as part of the troubleshooting effort to
understand why unusually high concentrations of oxygen were appearing
in the orbiter's payload bay. Once the team cleared the pad, tanking
commenced. The high readings of oxygen in the orbiter's midbody and
payload bay had stabilized but engineers continued to monitor them as
the countdown proceeded. Tanking started about 1.5 hours late and
engineers determined the excess oxygen in the payload bay was due to
trapped gas in the honeycomb structures of the payload bay. An earlier
concern with fuel cell No. 3 was cleared and the fuel cell was
operating properly. An additional check of the fuel cell's pH level
was taken at about T-3 hours before launch as a final confirmation.
-
- The seven members of the STS-82 crew were awakened at 7:30 tonight
and departed the Operations and Checkout Building for the pad at about
12:31am. Milestones for launch day (Reference KSC Press Release
20-97) start the day with close-out preparations in the white room and
the checking of cockpit switch configurations. Then at about 1:01
a.m. EST, the Flight crew begins entry into the orbiter and the
atronauts perform air-to-ground voice checks with Launch Control and
Mission Control. At about 2:26 a.m., Discovery's crew hatch should
close and the Eastern Range begins final network open loop command
checks. Then the hatch is sealed and cabin leak checks performed.
Then white room is closed-out and the Close-out crew moves to fallback
area.
- At L-1 day, Air Force weather forecasters indicated a 30 percent
probability of weather prohibiting launch on Tuesday. By launch day
that estimate was changed to 20 percent. A disturbance developing over
the South Central U.S. is expected to possibly increase cloudiness
through Monday. At launch time, the only concerns are for low and mid
level clouds. At launch time, the temperature at the pad is expected
to be about 56 degrees; relative humidity about 86 percent; clouds
scattered at 2,500 feet and 14,000 feet and broken at 25,000 feet; pad
winds from the northwest at 12-18 knots.
- On Sunday, Febuary 9, 1997, Pad 39A was cleared early in the
morning to load the onboard cryogenic tanks with liquid hydrogen and
liquid oxygen reactants. Reactant loading was completed and off-load of
several hundred pounds of the cryogenics not required for this mission
continued through most of the day. The reactants provide electricity
for the orbiter and crew while in space and drinking water as a
by-product for the 10-day mission. At about 10 a.m. on 2/10/97, checks
of the fuel cells were done to evaluate the pH content of the water
by-product. Also, engineers evaluated higher than allowable oxygen
readings in the orbiter's midbody following cryogenic loading
today. (Reference KSC Shuttle Status 2/09/1997)
- On Thursday, February 6, 1997, during aft close-out operations,
cycle tests on two aft engine compartment vent doors revealed an
intermittent failure of the doors to operate properly. Troubleshooting
of this problem concluded that the power drive unit (PDU) for the vent
doors had a bad circuit. Managers this afternoon decided to replace
the PDU. The additional work will delay aft close-outs but should
not impact launch on Tuesday. The aft doors are now scheduled to be
installed Saturday night. The countdown remains on schedule to begin
at 4 a.m. on February 8, 1997. (Reference KSC Shuttle Status 2/07/1997)
- The seven STS-82 crew members arrived at KSC on Friday, Feb. 7, at
7:30am. The launch countdown will begin at the T-43 hour mark at 4
a.m. EST Saturday, Feb. 8. Launch is currently targeted for 3:56
a.m. EST on Tuesday, Feb. 11, at the opening of a 65-minute launch
window. (Reference KSC Press Release 20-97)
- On 2/4/97, cryogenic servicing of the Near Infrared Camera and
Multi-Object Spectrometer (NICMOS) continued and the payload
end-to-end test began. Aft engine compartment close-outs continued and
the aft doors scheduled to be installed on Saturday (2/8/97). The crew
is scheduled to arrive at KSC Friday morning (2/7/97) and the
countdown is set to begin Saturday. (Reference KSC Shuttle Status 2/04/1997)
- On 1/31/97, during the Flight Readiness Review (FRR) in the
mission briefing room of the Operations and Checkout Building (O&C) at
KSC, the mission management team selected February 11, 1997 as the
official launch date for STS-82. (Reference KSC Shuttle Status 1/31/1997)
- On 1/29/97, payloads were installed into the orbiter's payload
bay and space suits used for the mission were installed into the
orbiters airlock. This weekend, workers will remove and replace
the Solid Rocket Booster (SRB) nozzle plugs from the SRBs at the pad.
(Reference KSC Shuttle Status 1/29/1997)
-
- On 1/17/97, Discovery began its journey from the VAB to the launch
pad shortly after 7 a.m. Rollout was stopped at approximately 8:25
a.m. after engineers heard a "load band" and noticed that a crack had
developed on deck plating of MLP-1. The 24-foot long "Y"-shaped crack
is on the surface of the MLP and runs from near the left hand SRB
flame hole toward the near corner of the MLP. Structural engineers
have determined the integrity of the MLP has not been compromised and
Discovery's trip to the launch pad resumed shortly after noon EST.
(Reference KSC Press Release 13-97)
- On 12/18/96, work on the airlock hatch actuators continued. The
Ku-band deployable assembly (DA) will be removed and replaced with
the DA from Columbia. A retest of the antenna is scheduled
for 12/19/96 and the payload bay doors will be closed for the
holidays on 12/20/96. (Reference KSC Shuttle Status 11/18/1996)
- The left hand orbital maneuvering system pod was installed on
11/16/96 and interface verification testing will begin 11/21/96. Fuel
cell No. 1 will be removed and replaced on Friday. Stacking of the
solid Vehicle Assembly Building. (Reference KSC Shuttle Status 11/20/1996)
- On 11/4/96, the orbiter docking system was stowed for flight and
the Auxiliary Power Unit (APU) #2 wiring work was completed.
(Reference KSC Shuttle Status 10/11/1996)
Orbit:
- Altitude: 360 statute miles
- Inclination: 28.45
- Orbits: 149
- Duration: 9 days, 23 hours, 38 minutes, 09 seconds.
- Distance: miles
Hardware:
- SRB: BI-085
- SRM:
- ET : SN-81
- MLP : MLP-1
- SSME-1: SN-2037
- SSME-2: SN-2040
- SSME-3: SN-2038
Landing:
- KSC 2/21/97 3:32 am EST. Landing at KSC Shuttle Landing Facility (SLF)
Runway 33. Main gear touchdown at 3:32:26 am EST (MET 9days 23hr 37min 09sec).
Nose gear touchdown at 3:32:37 am EST (MET 9days 23hours 37min 20sec) and
Wheel Stop at 3:33:26 am EST (MET 9days 23hours 38min 09sec).
- The first deorbit opportunity was on orbit 148 with an engine firing
at 11:38 p.m. CST followed by landing at 12:50 a.m. CST. This landing
opportunity was waived off due to cloud formation at the runway. (Reference KSC Weather History 02/21/1996 0000).
KSC's 2nd opportunity was selected and a 3.5 min deorbit burn occured at
2:21 am EST on orbit 149.
Mission Highlights:
STS-82 Flight Day 1 Highlights:
STS-82 Flight Day 2 Highlights:
STS-82 Flight Day 3 Highlights:
STS-82 Flight Day 4 Highlights:
STS-82 Flight Day 5 Highlights:
STS-82 Flight Day 6 Highlights:
STS-82 Flight Day 7 Highlights:
STS-82 Flight Day 8 Highlights:
STS-82 Flight Day 9 Highlights:
STS-82 Flight Day 10 Highlights:
STS-82 Flight Day 11 Highlights:
KSC Home Mission Index
Last Mission STS-81
Next Mission STS-83
Last Updated Friday June 29 11:36:57 EDT 2001
Jim Dumoulin (Redacted)
|