|
STS-109 (108)
- Columbia (27)
- Pad 39-A (74)
- 108th Shuttle Mission
- Night Launch (27)
- KSC Landing (58)
- Night Landing (19)
Crew:
- Scott D. Altman (3), Commander
- Duane G. Carey (1), Pilot
- John M. Grunsfeld (4), Payload Commander
- Nancy J. Currie (4), Mission Specialist
- James H. Newman (4) , Mission Specialist
- Richard M. Linnehan (3), Mission Specialist
- Michael J. Massimino (1), Mission Specialist
Milestones:
- OPF --
- VAB -- 1/16/2002 (Reference KSC Shuttle Status 1/17/2002)
- PAD -- 1/28/2002 (Reference KSC Shuttle Status 1/31/2002)
Payload:
- Hubble Space Telescope Servicing Mission 3
Mission Objectives:
Click here for Additional Info on STS-109
- Visit and service the Hubble Space Telescope. This mission will
- install a new science instrument, the Advanced Camera for Surveys
- (ACS), new rigid Solar Arrays (SA3), new Power Control Unit (PCU)
- and a new Cryocooler for the Near Infrared Camera and Multi-Object
- Spectrometer (NICMOS). STS-109 will also reboost HST to a higher
- orbit.
Launch:
- March 1, 2002 6:22:02 a.m. EST Launch Window was 64 minutes.
-
- On Friday, March 1, 2002, the 3 hour tanking operation was completed
at 12:13 a.m. The crew departed the Operations and Checkout (O&C)
Building and arrived at the launch pad shortly after 3a.m. EST. The
hatch was closed slightly later than planned due to one of the hatch
closeout microswitch indicators. The Orbiter Access Arm (OAA)
retracted at 6:15 a.m EST. Launch occured at the opening of the launch
window.
- On Wednesday, February 27, 2002, the Columbia's launch was postponed
until Friday, March 1st due to concerns about cold weather. Mission
managers were also meeting to discuss conerns about ball bearings
inside Columbia's main landing gear. On Thursday, the temperature at
the planned shuttle launch time was 38 degrees Fahrenheit (just inside
an acceptable range for launch). Temperature forcasts call for 55
degrees Fahrenheit at launch time on Friday. A Shuttle engineering
team completed an extensive evaluation of the landing gear bearing
issue and has determined there are no technical constraints that will
impact the STS-109 landing. (Reference KSC Shuttle Status 2/28/2002)
- On Monday, February 25, 2002, the launch countdown clock picked up
on schedule at the T-43 hour mark at 10 a.m. The STS-109 crewmembers
arrived at KSC at 1:00 a.m. this morning and spent about two hours
at Pad A performing a final inspection of the HST payload.
(Reference KSC Shuttle Status 2/25/2002)
- On Friday, February 22, 2002, final pre-launch processing for Shuttle
Columbia continues on schedule at Complex 39 Pad A . The Hubble
payload Interface Verification Test is complete and the End-To-End
Test is in progress. Work over the weekend includes completing aft
closeouts prior to picking up the final countdown at the T-43 hour
mark at 10 a.m. Monday, Feb. 25. The seven STS-109 crewmembers are
scheduled to land at KSC at 1 a.m. Monday, and shortly after their
arrival they will spend about two hours at the launch pad
participating in final Hubble payload configuration familiarization
operations in preparation for the five spacewalks that will be
conducted during the STS-109 servicing mission. The payload doors will
be closed later in the day. The status of the Auxiliary Power Unit
hydraulic pump bolts is still under evaluation. (Reference KSC Shuttle
Status 2/22/2002)
On 1/28/02, Shuttle Columbia rolled out to Launch Complex 39A and is
undergoing final preparations. The main engine Flight Readiness Test
is complete and the two-day Countdown Demonstration Test (CDT) is
underway, with a T-0 at 11 a.m. on Friday. The seven STS-109
crewmembers will be at the launch pad for familiarization and
emergency egress operations today and will be onboard Columbia
tomorrow to participate in the final hours of the simulated countdown.
(Reference KSC Shuttle Status 1/31/2002)
-
- The rollout of Shuttle Columbia from the Vehicle Assembly Building
(VAB) to Pad 39A was rescheduled for no earlier than Saturday morning
due to requirements to continue trouble-shooting and verifying a
faulty bearing in the steering linkage on one of the
crawler-transporter's (CT) four "trucks." In addition, NASA management
mandated that all of the trucks on the CT be inspected and verified
prior to commencing rollout activities. The rollout had been scheduled
for Wednesday, Jan. 23, but was delayed due to th crawler problem. No
impact to the prelaunch milestones or launch date is expected.
(Reference KSC Shuttle Status 1/24/2002)
- On January 17, 2002, Columbia rolled over from the OPF into the
Vehicle Assembly Building (VAB). (Reference KSC Shuttle Status 1/17/2002)
- The launch date for STS-109 was earlier pushed back to give
engineers time to evaluate a reaction wheel problem on the Hubble
Space Telescope. Previous launch dates were February 14, 2002,
January 17, 2002, January 11, 2001 and before that November 19, 2001.
Orbit:
- Altitude: 308nm
- Inclination: 28.5
- Orbits: 165
- Duration: 10 days, 22 hours, 11 minutes, 09 seconds.
- Distance: 3.9 million miles
Hardware:
- SRB:
- SRM:
- ET :
- MLP :
- SSME-1: SN-
- SSME-2: SN-
- SSME-3: SN-
Landing:
- KSC March 12, 2002 EST (4:32 a.m. EST / 09:32 GMT). Runway 33.
- Deorbit engines fired at 3:22 a.m. EST (08:22 GMT).
Touchdown Times:
- Main Gear Touchdown 4:31:52 a.m. EST (MET: 10 days 22 hours 9 min 51 sec)
- Nose Gear Touchdown 4:32:02 a.m. EST (MET: 10 days 22 hours 10 min 1 sec)
- Wheel Stop: 4:33:09 a.m. EST (MET: 10 days 22 hours 11 min 9 sec)
Mission Highlights:
KSC Home Mission Index
Last Mission STS-108
Next Mission STS-110
Last Updated Monday April 1 17:50:54 EDT 2002
Jim Dumoulin (Redacted)
|